JULY 8, 2014 SITE UPDATE – CRAVEN STREET
Posted on the New Belgium Brewing website Tuesday, July 08, 2014.
We have a shift in the pile driving schedule from our Early July Update. Thank you for bearing with us during this construction process, which is, at times unpredictable, with timelines and processes shifting day by day and sometimes even hour by hour. We’re doing our best to keep you posted. Update below.
Good news –Pile driving will stop temporarily. We anticipate this temporary stop happening by the end of the week of July 7, earlier than our original estimated stop date of mid to end of July.
Bad news – While we wish it were complete, pile driving is not yet finished. We anticipate we will drive about 40 additional piers starting in late summer or early fall. We will keep you posted as to when it will restart and do our best to approximate the duration at that time. Our best estimate, at this time, is that it will take a total of about three additional weeks once the pile driving resumes (making up the remaining weeks we will not be driving during the rest of July).
Questions or Comments? Maybe we’ll see you at the RAD Farmers Market at All Souls Pizza on Wednesday, July 9? Or maybe the West Asheville Tailgate Market on Tuesday, July 22? We’d like to meet you, please come by or, if you can’t make it and want to get in touch, give us a call 828-333-6900.