City crews milling and patching Vermont Avenue over the past several weeks found that the sub-grade of the West Asheville road was in much worse shape than expected, requiring extensive patching in order to ensure the quality of the new surface. In this video, Director of Public Works Greg Shuler explains how extra crews are working extra hours with a goal of completing the patching within the next two weeks, at which time, the contractor can put down new asphalt.
Thank you to all of the residents for your patience during this process.