NBB – Oversized Delivery: Wednesday, Jan 7, 2015

Wednesday, Jan. 7 – Whirlpool (first oversized) arrives Time: We’re hoping it will be to the site by noon.  It is legally able to travel until 5 p.m. First oversized vessel arrival – The whirlpool vessel arrival will require rolling delays from I-40 to NC 191 to I-240 to Exit 2 to Hanover Street to Haywood Road to 91 […]

New Belgium Brewing Oversized Deliveries

New Belgium Brewing is entering an exciting phase in their construction process which includes delivery of oversized brewing equipment. Most of these deliveries will route along Haywood Road from I-240, Exit 2 eastward to Craven Street and require no special considerations. There are also a few deliveries that will require special routing and rolling road closures. ****** […]

Craven Street Improvement Project Moves to Next Phase

ASHEVILLE – The Craven Street improvement project underway in west Asheville moves to the next phase this week. The stormwater culvert section of the project underway since mid-July is complete and crews will shift to the realignment of Craven Street, Emma Road and Hazel Mill Road. Work along this section is anticipated to take through […]

NBB Updates: Hiring Couple Positions

The bulk of public hiring starts in 2015, but we wanted to let you know that we’ve posted a couple of Asheville jobs.  Bookmark this page and check back often if you’re interested!  http://www.newbelgium.com/brewery/company/view-and-apply.aspx

NBB Updates: October 31, 2014

HAPPENING NOW Deep Foundation Piles – Anticipated neighborhood impact: 4 of 5 (noise and trucks) The second and final planned installation of deep foundation piles will start around November 10 and be finished within two weeks or less, weather pending. We thank our immediate neighbors for their patience during this process. Given the generally unstable […]

Haywood Road restriping in time for Craven Street closure

ASHEVILLE – A stretch of Haywood Road leading from the French Broad River into West Asheville will get a new look beginning Thursday, August 21, as crews relocate the center yellow line and add a climbing bicycle lane. The work is being conducted ahead of the August 28 closing of Craven Street between Haywood Road […]

New Belgium Brewing August 7, 2014: Site Update-Craven Street

HAPPENING NOW Concrete Foundation Work–Anticipated neighborhood impact: 3 of 5 (expanded work hours and concrete trucks) Foundation work has begun and runs through the first of next year.  You will see increased trucks along Riverside Dr. and Craven St., and you may see some on Haywood Rd.  You will see material deliveries and trucks on […]

New Belgium Brewing Early July Site Updates

JULY 8, 2014 SITE UPDATE – CRAVEN STREET Posted on the New Belgium Brewing website Tuesday, July 08, 2014. We have a shift in the pile driving schedule from our Early July Update. Thank you for bearing with us during this construction process, which is, at times unpredictable, with timelines and processes shifting day by day and sometimes even hour […]