NBB Updates: October 31, 2014

HAPPENING NOW Deep Foundation Piles – Anticipated neighborhood impact: 4 of 5 (noise and trucks) The second and final planned installation of deep foundation piles will start around November 10 and be finished within two weeks or less, weather pending. We thank our...

New Belgium Brewing Early July Site Updates

JULY 8, 2014 SITE UPDATE – CRAVEN STREET Posted on the New Belgium Brewing website Tuesday, July 08, 2014. We have a shift in the pile driving schedule from our Early July Update. Thank you for bearing with us during this construction process, which is, at times...

NBB MAY 2014 SITE UPDATE: MONTHLY OVERVIEW

MAY 2014:  Preparing site for building construction Anticipated neighborhood impact: 4 of 5 (noise and trucks) The focus remains on preparing the site for building construction, and the end of this phase is in sight!  Although the early-spring wet weather caused...